April 2004--Passero Associates
was recently honored to receive a “Project of the Year”
award from the Monroe County Genesee Valley Branch of the American
Public Works Association (APWA) for the Webster Sandbar Sewer
and Water Extension. The award was in the $2 to $10 million Environmental
Projects category. Award recipients included project partners:
the Town of Webster, the Monroe County Department of Environmental
Services – Pure Waters Department, the Monroe County Water
Authority; and private sector participants Passero Associates
for engineering design and construction management, and Villager
Construction as the primary contractor.
The Webster Sandbar Sewer and Watermain Extension
is the result of a collaborative effort between the Town and the
County to provide sewer and water facilities to the Sandbar area
and to protect its unique environmental features. The Sandbar
is a picturesque area approximately one mile in length at the
Ontario Lake inlet to Irondequoit Bay. Over 200 residential and
commercial properties, many of which were on were on troublesome
private septic systems, benefit from the new public sanitary sewer.
The sewer also eliminates the flow of untreated sewage into Irondequoit
Bay and Lake Ontario, ends possible contamination of the groundwater,
and improves the natural ecosystem of the area. The project required
the latest pipeline installation methods to overcome the numerous
challenges encountered along the Sandbar.
The Sandbar sewer and watermain project was
a culmination of several years of planning and studies. Monroe
County Pure Waters had sought a way to convey sewage from 1500
units in their Penfield service area to the Van Lare WWTP where
it could be treated more economically. Webster studied ways it
could extend sanitary sewers to the sandbar in a way it would
be affordable for the property owners. MCWA wanted to improve
its domestic and fire-fighting services to the sandbar area. In
2000, the three agencies saw the benefits of collaborating on
the project to achieve their objectives more cost-effectively
versus doing it independently.
The project consisted of the construction of
two (2) pump stations and approximately 5,600 LF of 12'' HDPE
force main to convey the flow collected in Webster and Penfield
to the MCPW interceptor in Irondequoit. The MCPW pump station
is a duplex submersible design with two 50 HP pumps capable of
delivering 1200 gpm at 90' of head. The Webster pump station which
collects flow from the western half of the Sandbar and pumps it
to MCPW PS is a duplex self-priming 10 HP pumps capable of delivering
100 gpm at 69' of head. The project also included the installation
of approximately 10,100 LF of 8''-15'' PVC gravity sewer main
and 4'' PVC sanitary laterals to provide service connections to
approximately 200 properties. The project utilized several best
management practices to minimize impact on sensitive environmental
areas from construction through use of directional drilling, dewatering
and sewer boring technologies. Road pavement, driveways and lawn
areas that were disturbed were restored to match original conditions.
All proposed work was performed within public right-of-ways and
easements which the Town and County acquired.
The Sandbar area contains several significant
environmental areas which required extensive deliberations with
permit agencies to demonstrate that the project properly addressed
these issues. Among the environmental features in the project
area are wetlands, coastal hazards areas, flood zones, fish and
wildlife habitat and archaeological sites. During the design process,
the engineering consultant met with the sixteen review agencies
involved to arrive at the best solution which caused the least
impact to these areas while achieving the project goal of eliminating
discharge of sewage to Lake Ontario and Irondequoit Bay.
The construction cost for the project was $4.4
million. The funding for this project was obtained via the following
sources: State’s EFC Revolving Loans of $1 million for the
Town of Webster and $2.5 million for MCPW, $500,000 cash capital
from MCWA; and the State’s Clean Water Bond Act grant for
$500,000.
The construction contract was awarded to Villager
Construction in September 2002. Villager was given a notice to
proceed in November 2002. Villager continued work on the project
through one of the harshest winters in recent memory and completed
the project in December 2003. The sewer system is now fully operational.
|